Note: The department recognizes pollution control equipment start-up problems may arise at the commencement of a new discharge. Enforcement discretion may be used in the 90 days following commencement of discharge, in such cases.
Wis. Admin. Code Department of Natural Resources § NR 106.117
An interim permit requirement is not necessarily a numerical effluent limitation.
Note: Compliance schedule provisions for TMDL-based limits, technology-based limits, and phosphorus limits may differ from the requirements of this section. These provisions may be found in ss. NR 212.75(5), 205.14, and 217.17, respectively