Section DHS 159.20 - Asbestos abatement notification
(1) NOTIFICATION REQUIREMENT. Before it may set up to perform an asbestos abatement activity, an asbestos company shall notify the department as required under this section on a form obtained from or approved by the department and shall pay the applicable fee specified under sub. (8).
(2) ABATEMENT ACTIVITIES THAT REQUIRE NOTIFICATION.
(a) An asbestos company shall notify the department of any of the following asbestos abatement activities performed on the interior or exterior of a residential structure that has fewer than 5 dwelling units:
1. Removal of more than one glove bag or disposal bag, which is no larger than 60 inches by 60 inches properly filled and sealed, of friable or non-friable asbestos-containing material.
2. Enclosure, encapsulation or repair of more than 3 square feet or 3 linear feet of friable asbestos-containing material.
(b) An asbestos company shall notify the department of any of the following asbestos abatement activities performed on the interior or exterior of any facility other than a residential structure that has fewer than 5 dwelling units:
1. Removal of more than one glove bag or disposal bag, which is no larger than 60 inches by 60 inches properly filled and sealed, of non-friable asbestos-containing material.
2. Removal of more than one glove bag or disposal bag, which is no larger than 60 inches by 60 inches properly filled and sealed, but less than 160 square feet, 260 linear feet, 35 cubic feet of friable asbestos-containing material, or less than 5,580 square feet of asbestos-containing roofing using mechanical methods.
3. Enclosure, encapsulation or repair of more than 3 square feet or 3 linear feet of friable asbestos-containing material.
(3) EXCEPTIONS TO NOTIFICATION. Notification is not required when removal is conducted before a fire burn or demolition regulated under ch. NR 447 and notification is made to the Wisconsin department of natural resources.

Note: The Department of Natural Resources also has notification requirements under ch. NR 447 that apply to structures other than residential structures with fewer than 5 dwelling units. Notification to the DNR is required before the removal of any amount of asbestos-containing material for DNR-regulated demolitions and before the removal of friable asbestos or regulated asbestos-containing material in amounts of 160 sq. ft., 260 lnr. ft., or 35 cu. ft., or more, for renovation and planned renovation projects. For more information on DNR requirements, visit the DNR website at http://dnr.wi.gov and type in keyword "asbestos" in the Site Search.

(4) REQUIRED CONTENT OF NOTIFICATION. Notification shall include all of the following:
(a) A unique company project number assigned by the asbestos company.
(b) The following information regarding the asbestos abatement activity site: type of property, property name if applicable, address, and the name and telephone number of the authorized property contact person.
(c) The asbestos abatement type: removal, enclosure, encapsulation or repair of asbestos-containing material, or any combination of these activities.
(d) The occupancy status: whether the structure will be occupied or vacant during the project.
(e) The notification type: original, cancellation, revision, planned renovation project, or sub-project to a planned renovation project.
(f) The asbestos abatement activity schedule including start date beginning with set up, end date, and work days and hours.
(g) Information about any pre-project asbestos inspection conducted and the name and department certification number of the inspector.
(h) The asbestos company name, department certification number and address, and the name and telephone number of the project contact person.
(i) The amount and type of asbestos-containing material involved in the project.
(j) Signature of an authorized company representative and the date of signature.
(5) NOTIFICATION FOR PLANNED RENOVATION.
(a) An asbestos company may submit notification for a planned renovation project, for a time period not to exceed 12 months, when the company anticipates that multiple sub-projects of a planned renovation will include asbestos abatement activities. A company submitting notification for a planned renovation shall subsequently submit notification for each asbestos sub-project that meets the notification requirements under sub. (1).
(b) Notification for a sub-project to a notified planned renovation project shall include all of the following:
1. The company project number for the planned renovation from the original planned renovation notification.
2. The sequential number of the asbestos sub-project conducted under the planned renovation project.
3. All other asbestos abatement activity information required under sub. (2).

Note: Department notification forms are available on the department's website at www.dhs.wi.gov/ asbestos or may be obtained from the Asbestos and Lead Unit: plicasbstoslead@dhs.state.wi.us; 608-261-6876; 1 W. Wilson St, Room 137, PO Box 2659, Madison, WI 53701-2659.

(6) NOTIFICATION OF REVISED OR CANCELLED PROJECT.
(a) Whenever any information required under sub. (2) changes or when a project is cancelled, the asbestos company shall submit a revised notification to the department using a copy of the original notification with the following:
1. In the section labeled "notification type" on the notification form, either "cancellation" or "revision" checked and the number of the revision entered.
2. All revised information circled or highlighted.
(b) A notification of revision or cancellation shall be submitted as soon as the need for revision or cancellation is known, accompanied by the appropriate fee if required under sub. (8) (b).
(c) An asbestos abatement activity notification is considered expired once the abatement activity has been cancelled or the abatement activity end date has passed. A notification may be revised after it expires only if the project fails air clearance and re-cleaning is necessary. "Re-cleaning" shall be clearly stated on the revised notification form.
(d) If an expired asbestos abatement activity is rescheduled, a new notification and fee is required.

Note: Submit revised notifications by fax, 608-266-9711; email, plicasbestoslead@dhs.state.wi.us or personal delivery to Room 137, 1 W. Wilson St, Madison, WI.

(7) NOTIFICATION SUBMITTAL.
(a) Original asbestos abatement activity notification and planned renovation project notification and fees may be submitted by means of fax, email, personal delivery, delivery service, another method if approved by the department, or by U.S. postal service if postmarked at least 4 working days before the project start date. U.S. postal service may not be used when submitting notification less than 4 working days before the asbestos abatement activity start date.
(b) Revised and cancelled asbestos abatement activity notification may be submitted by means of fax, email, personal delivery, or another method if approved by the department.
(8) NOTIFICATION FEES. The appropriate fee shall accompany the asbestos abatement activity notification.
(a) For an original asbestos abatement activity notification, the following fees apply:
1. A $50 fee when submitted to the department 2 working days or more before the project start date. Notification submitted by U.S. postal service that is postmarked at least 4 working days before the project start date will be deemed in compliance with a 2 working day notification.
2. A $100 fee when submitted to the department less than 2 working days before the project start date.
(b) For revisions to an asbestos abatement activity notification, the following fees apply:
1. A $50 fee when a revision to an earlier start date is submitted to the department less than 2 working days before the new start date.
2. No fee is required with any other revision submitted to the department.
(c) For an original planned renovation project or sub-project notification, the following fees apply:
1. A $100 fee for an original planned renovation project notification.
2. A $50 fee for a sub-project notification when submitted to the department less than 2 working days before the sub-project start date.
3. No fee for a sub-project notification when submitted to the department 2 working days or more before the sub-project start date.
(d) An asbestos abatement activity notification fee shall be paid by the following means:
1. When submitting notification by fax or email, payment shall be made by credit or debit charge to VISA or MasterCard.
2. When submitting notification by personal delivery, delivery service, or U.S. postal service, payment may be made by check, money order, or credit or debit charge to VISA or MasterCard.
3. The department does not accept cash payment.
4. Payment by check or money order shall be made payable to "Department of Health Services" or "DHS".
(e) A person who submits a fee that is not honored by a financial institution may be required to submit the fee in a form of payment that is guaranteed by a financial institution and to pay any processing charges.
(f) Fees are nonrefundable and nontransferable.
(g) A school that is subject to AHERA regulations is exempt from notification fees when the asbestos abatement activity is conducted solely by a school district employee.

Wis. Admin. Code Department of Health Services DHS 159.20

CR 08-036: cr. Register February 2009 No. 638, eff. 5-1-09.

Submit notification to Asbestos and Lead Unit: 1 W. Wilson St, Room 137, PO Box 2659, Madison, WI 53701-2659; (fax) 608-266-9711; plicasbestoslead@dhs.state.wi.us. For notification submitted by fax or email payment may be made only by credit or debit charge to a VISA or MasterCard.