W. Va. Code R. § 47-26-6

Current through Register Vol. XLI, No. 45, November 8, 2024
Section 47-26-6 - Permit Modification Application Fees
6.1. Fee Calculation. Except as provided in subsections 6.2 through 6.7 of this rule, all permit modification application fees will be calculated through the use of the following formula: the permit modification application fee shall equal the volume fee multiplied by the facility factor multiplied by the waste factor (i.e., Permit Modification Application Fee = Volume Fee x Facility Factor x Waste Factor).
6.1.1. The appropriate volume fee will be determined through the use of the "Existing Facility" column of Table A of this rule. Only the discharge volume of the activity affected by the modification shall be used in determining the appropriate volume fee.
6.1.2. The appropriate facility factor will be determined through the use of Table B of this rule.
6.1.3. The appropriate waste factor will be determined through the use of Table C of this rule.
6.2. Publicly-Owned Treatment Works.
6.2.1. The permit modification application fee for a POTW that operates a collection system only will be ten percent (10%) of the initial permit application fee for an application seeking a major modification.
6.2.2. The permit modification application fee for a POTW that operates a collection system only will be two percent (2%) of the initial permit application fee or fifty dollars ($50), whichever is greater, for an application seeking a minor modification.
6.3. Closed System Facilities.
6.3.1. The permit modification application fee for a closed system facility will be ten percent (10%) of the initial permit application fee for an application seeking a major modification.
6.3.2. The permit modification application fee for a closed system facility will be two percent (2%) of the initial permit application fee or one hundred dollars ($100), whichever is greater, for an application seeking a minor modification.
6.4. Solid Waste Facilities. The permit modification application fee for a solid waste facility will be set and collected in accordance with the provisions of 33CSR1.
6.5. Non-Volume-Related Major Modifications. Except as provided in subsections 6.2 through 6.4 of this rule, the permit modification application fee will be ten percent (10%) of the initial permit application fee for sewage facilities and ten percent (10%) of the initial permit application fee, or five hundred dollars ($500) whichever is greater for industrial facilities for an application seeking a major modification where no discharge volume is involved.
6.6. Non-Volume-Related Minor Modifications. Except as provided in subsections 6.2 through 6.4 of this rule, the permit modification application fee will be fifty dollars ($50) for sewage only facilities and one hundred dollars ($100) for industrial facilities for an application seeking a minor modification where no discharge volume is involved.
6.7. Concentrated Animal Feeding Operations. The permit modification application fee for a CAFO shall be thirty-five dollars ($35) for an application seeking a major or minor modification.

W. Va. Code R. § 47-26-6