W. Va. Code R. § 38-8-9

Current through Register Vol. XLI, No. 44, November 1, 2024
Section 38-8-9 - Modifications
9.1. The operator, in addition to any revisions or modifications to the mine safety program made in accordance with Section 8.1 of these rules and regulations, may submit at any time, proposed modifications or revisions along with the reasons therefore, to the Commissioner.
9.2. Within thirty (30) days after receipt by the Commissioner of any proposed revisions or modifications to the program, the Commissioner shall either approve the revisions, or reject the revisions, stating in detail the reasons for such rejection. If within thirty (30) days of receipt of such revisions by the Commissioner no action has been taken, the proposed revisions shall be taken as approved.
9.3. When revisions to a program are submitted to the Commissioner, the operator may request and the Commissioner may issue temporary approval of such revisions pending the Commissioner's final review and approval.

W. Va. Code R. § 38-8-9