Current through Register Vol. XLI, No. 44, November 1, 2024
Section 38-4-5 - Application Procedures5.1. Application Preparation and Submission.5.1.a. Applications for a certificate of approval will be prepared by or under the direct supervision of an engineer.5.1.b. Application for certificate of approval shall be submitted in a form prescribed by the Secretary. The application shall be signed by the applicant and an engineer.5.1.c. A complete application will consist of a completed and signed application form, applicable fees, design report and a plan package containing information required under Section 6.4 of these rules.5.1.d. Plans, design report, specifications and design drawings shall be signed and sealed by an engineer in accordance with the provisions of Section 6.2 of these rules.5.2. Application Review. 5.2.a. Application of certificate of approval will be reviewed for completeness and technical accuracy of information submitted, an evaluation of all engineering plans and assumptions to determine the safety of the dam and the impoundment.5.2.b. Applications which are incomplete or otherwise not in compliance with the requirements of these rules will be returned to the applicant for correction in accordance with the provisions of W. Va. Code § 22-14-7.