Electric vehicle supply equipment (EVSE) shall be installed in accordance with applicable requirements of chapter 19.28 RCW and the National Electrical Code, Article 625.
EXCEPTION: | Electric vehicle charging infrastructure is not required if any of the following conditions are met: |
1. There is no public utility or commercial power supply. | |
2. Dwelling units without garages or other on-site parking. |
EXCEPTIONS: | 1. Except for Group A, Group E, and Group M occupancies, on-site parking with less than 10 parking spaces shall not be required to comply with Section 429.2. |
2. Group A, Group E, and Group M occupancies shall comply with one of the following, whichever is greater: | |
2.1. The provisions of Section 429.2 shall apply only to designated employee parking spaces. | |
2.2. One of each 200 parking spaces or fraction thereof shall be EV Ready. One of each 200 parking spaces or fraction thereof shall be an EV Charging Station. |
Table 429.2 Electric Vehicle Charging Infrastructure
Occupancy | Number of EV Charging Stations | Number of EV-Ready Parking Spaces | Number of EV-Capable Parking Spaces |
Group A, B, E, F, H, I, M, and S occupancies | 10% of total parking spaces | 10% of total parking spaces | 10% of total parking spaces |
Group R occupancies | |||
Buildings that do not contain more than two dwelling units | Not required | One for each dwelling unit | Not required |
Dwelling units with private garages | Not required | One for each dwelling unit | Not required |
All other Group R occupancies | 10% of total parking spaces | 25% of total parking spaces | 10% of total parking spaces |
The electrical service and the electrical system, including any on-site distribution transformer(s), shall have sufficient capacity to simultaneously charge all EVs at all required EV Charging Stations, EV Ready parking spaces, and EV-Capable parking spaces at a minimum of 40-amperes each.
EXCEPTION: | Automatic Load Management System (ALMS) may be used to adjust the maximum electrical capacity required for the EV-Ready and EV-Capable parking spaces. The ALMS must be designed to allocate charging capacity among multiple future EV Charging Stations at a minimum of 16 amperes per EV charger. |
The electric vehicle charging infrastructure may also serve adjacent parking spaces not designated as accessible parking. A maximum of 10 percent of the accessible parking spaces, rounded to the next whole number, are allowed to be included in the total number of electric vehicle parking spaces required under Section 429.2.
Wash. Admin. Code § 51-50-0429