EXCEPTION: | Buildings, or portions thereof, which are exempt from Sections C408.2 through C408.7 may be excluded from the commissioning process. |
1. Mechanical systems that are not required to comply with Section C403.3.5 are exempt from the commissioning process where the installed total mechanical equipment capacity is less than 180,000 Btu/h (15 tons) cooling capacity and less than 240,000 Btu/h (20 tons) heating capacity and energy recovery ventilation (ERV) equipment is less than 300 cfm capacity. | |
2. Service water heating systems are exempt from the commissioning process in buildings where the largest service water heating system capacity is less than 200,000 Btu/h and where there are any of the following: | |
2.1. No pools or permanent spas. | |
2.2. No solar thermal water heating. | |
2.3. No recirculation pumps. | |
2.4. No heat pump water heaters, except fully-packaged for individual residential dwelling unit use. | |
3. Lighting control systems are exempt from the commissioning process in buildings where both the total installed lighting load is less than 10 kW and the lighting load controlled by occupancy sensors or automatic daylighting controls is less than 5 kW. | |
4. Refrigeration systems are exempt from the commissioning process in buildings if they are limited to self-contained units. |
EXCEPTION: | Deferred tests which cannot be performed at the time of report preparation due to climatic conditions. |
Wash. Admin. Code § 51-11C-40801
Statutory Authority: RCW 19.27A.020, 19.27A.025 and chapters 19.27 and 34.05 RCW. 13-04-056, § 51-11C-40801, filed 2/1/13, effective 7/1/13.