Wash. Admin. Code § 480-75-410

Current through Register Vol. 24-12, June 15, 2024
Section 480-75-410 - Coatings

Before backfilling, each pipeline company must electrically inspect all new coated pipe used to transport hazardous liquids, using a holiday detector to check for faults not observable by visual examination. The pipeline company shall operate the holiday detector in accordance with the manufacturer's instructions and at the voltage level appropriate for the electrical characteristics of the pipeline being tested.

Wash. Admin. Code § 480-75-410

Statutory Authority: RCW 80.01.040, 80.04.060, 81.88.040. 08-12-045 (Docket PL-070974, General Order R-548), § 480-75-410, filed 5/30/08, effective 6/30/08. Statutory Authority: RCW 80.01.040 and 80.04.160. 02-18-032 (Docket No. TO-000712, General Order No. R-500), § 480-75-410, filed 8/26/02, effective 9/26/02.