Wash. Admin. Code § 480-103-050

Current through Register Vol. 25-01, January 1, 2025
Section 480-103-050 - Disconnection of service

An electric utility is not liable for incentive payments to a community solar company's project participants if the utility has disconnected utility service to the company due to the company's violation of a customer service agreement, such as nonpayment of the company's utility bill, or the company's violation of the interconnection agreement between the company and the utility.

Wash. Admin. Code § 480-103-050

Adopted by WSR 18-20-098, Filed 10/2/2018, effective 11/2/2018