Wash. Admin. Code § 463-78-115

Current through Register Vol. 24-20, October 15, 2024
Section 463-78-115 - Standards of performance for new stationary sources
(1)Title 40, Code of Federal Regulations, Part 60 (standards of performance for new stationary sources), in effect on July 1, 2014, as applicable to new stationary sources subject to chapter 80.50 RCW is by this reference adopted and incorporated herein with the exception listed in subsection (2) of this section. For the purpose of state administration of the federal regulations adopted by reference hereby, the term "administrator" as used therein shall refer to the council. The following list is provided for informational purposes only:

Subpart A General Provisions, except C.F.R. 60.5 and 60.6
Subpart D Fossil fuel fired steam generators for which construction commenced after August 17, 1971, and prior to September 19, 1978, which have a heat input greater than 73 megawatts but not greater than 350 megawatts
Subpart Da Electric utility steam generating units for which construction commenced after September 18, 1978, which have greater than 73 megawatts but not greater than 350 megawatts
Subpart J Petroleum refineries which produce less than 25,000 barrels per day of refined products
Subpart Ja Standards of performance for petroleum refineries for which construction, reconstruction, or modification commenced after May 14, 2007
Subpart K Storage vessels for petroleum liquid constructed after June 11, 1973, and prior to May 19, 1978, which have a capacity greater than 40, 000 gallons
Subpart Ka Storage vessels for petroleum liquids constructed after May 18, 1978, which have a capacity greater than 40,000 gallons
Subpart Kb Volatile organic liquid storage vessels (including petroleum liquid storage vessels) constructed, reconstructed, or modified after July 23, 1984
Subpart Y Standards for Performance for Coal Preparation Plants
Subpart GG Stationary gas turbines
Subpart VV Standards of performance for equipment leaks of VOC in the synthetic organic chemicals manufacturing industry for which construction, reconstruction, or modification commenced after January 5, 1981, and on or before November 7, 2006
Subpart VVa Standards of performance for equipment leaks of VOC in the synthetic organic chemicals manufacturing industry for which construction, reconstruction, or modification commenced after November 7, 2006
Subpart XX Bulk gasoline terminals
Subpart GGG Petroleum refineries - compressors and fugitive emission sources
Subpart KKK Equipment leaks of VOC from onshore natural gas processing plants
Subpart LLL Onshore natural gas processing; SO2 emissions
Subpart NNN VOC emissions from SOCMI distillation operations
Subpart QQQ VOC emissions from petroleum refinery wastewater emissions
Subpart RRR Standards of performance for volatile organic compound emissions from synthetic organic chemical manufacturing industry (SOCMI) reactor processes
Subpart IIII Standards of performance for stationary compression ignition internal combustion engines
Subpart JJJJ Standards of performance for stationary spark ignition internal combustion engines
Subpart KKKK Standards of performance for stationary combustion turbines
Appendix A Test Methods
Appendix B Performance Specifications
Appendix C Determination of Emission Rate Change
Appendix D Required Emission Inventory Information
Appendix F Quality Assurance Procedures

(2) The following sections of 40 C.F.R. Part 60 are not adopted by reference:
(a) Sections 60.5 (Determination of Construction or Modification) and 60.6 (Review of Plans);
(b) 40 C.F.R. Part 60, subpart B (Adoption and Submittal of State Plans for Designated Facilities), and subparts C, Cb, Cc, Cd, Ce, BBBB, and DDDD (emission guidelines); and
(c) 40 C.F.R. Part 60, Appendix G, Provisions for an Alternative method of Demonstrating Compliance with 40 C.F.R. 60.43 for the Newton Power Station of Central Illinois Public Service Company.

Wash. Admin. Code § 463-78-115

Amended by WSR 15-16-033, Filed 7/27/2015, effective 8/27/2015

Statutory Authority: RCW 80.50.040(1) and (12). 06-06-037, § 463-78-115, filed 2/23/06, effective 3/26/06; 04-21-013, recodified as § 463-78-115, filed 10/11/04, effective 11/11/04; 04-17-058, § 463-39-115, filed 8/11/04, effective 9/11/04. Statutory Authority: RCW 80.50.040(1). 94-16-031, § 463-39-115, filed 7/26/94, effective 8/26/94; 92-09-013, § 463-39-115, filed 4/2/92, effective 5/3/92; 82-14-051 (Order 82-3), § 463-39-115, filed 6/30/82; 79-09-006 (Order 79-1), § 463-39-115, filed 8/6/79.