Current through Register Vol. 24-21, November 1, 2024
Section 388-97-3480 - New construction timelines(1) Construction documents must be resubmitted for review as a new project according to current requirements if construction: (a) Has not started within one year from the date of approval; or(b) Is not completed within two years from the date of approval.(2) To obtain an extension beyond two years, a written request must be submitted and approved thirty days prior to the end of the two-year period.Wash. Admin. Code § 388-97-3480
Statutory Authority: Chapters 18.51 and 74.42 RCW and 42 C.F.R. 489.52. 08-20-062, § 388-97-3480, filed 9/24/08, effective 11/1/08.