Wash. Admin. Code § 296-150F-0230

Current through Register Vol. 24-23, December 1, 2024
Section 296-150F-0230 - What are the insignia application requirements?
(1) If you are requesting insignia for units that you intend to manufacture under a new design plan, your completed application must include:
(a) A completed design plan approval request form;
(b) Two complete sets of design plans, specifications, engineering analysis, test procedures and results, plus one additional set for each manufacturing location where the design plan will be used;
(c) At least one set of design plans must have an original wet stamp from a professional engineer or architect licensed in Washington state. We will retain the set with the original wet stamp; and
(d) A one-time initial filing fee, the design plan fee (if we approve your design plan) and the fee for each insignia. (See WAC 296-150F-3000.)
(2) If you are requesting insignia under an approved design plan, your completed application must include:
(a) A completed application for insignia form; and
(b) The fee for each insignia requested. (See WAC 296-150F-3000.)

Wash. Admin. Code § 296-150F-0230

Statutory Authority: Chapter 43.22 RCW. 12-15-061, § 296-150F-0230, filed 7/17/12, effective 9/1/12. Statutory Authority: RCW 43.22.340, [43.22.]355, [43.22.]360,[43.22.]432 , [43.22.]440 and [43.22.]480. 96-21-146, § 296-150F-0230, filed 10/23/96, effective 11/25/96.