Section 246-236-015 - Commencement of construction(1) Commencement of construction of a new irradiator may not occur prior to the submission to the department of both an application for a license for the irradiator and the fee required by chapter 246-254 WAC.(2) Any activities undertaken prior to the issuance of a license are entirely at the risk of the applicant and have no bearing on the issuance of a license with respect to the requirements of chapter 70A.388 RCW, and rules and administrative orders issued under chapters 34.05 and 70A.388 RCW.(3) Commencement of construction as defined in WAC 246-236-010 may include nonconstruction activities if the activity has a reasonable nexus to radiological safety and security.Wash. Admin. Code § 246-236-015
Adopted by WSR 18-15-017, Filed 7/9/2018, effective 8/9/2018Amended by WSR 22-07-025, Filed 3/9/2022, effective 4/9/2022