Current through Register Vol. 24-23, December 1, 2024
Section 173-95A-560 - Process for water pollution control activities The following process is required for lake projects and recommended for all water pollution control activities projects.
(1)Planning involves the identification of problems , evaluation of cost-effective alternatives in accordance with WAC 173-98-730, and preparation of a planning document.(2)Implementation is the actual implementation of the project based on the planning document. Wash. Admin. Code § 173-95A-560
Amended by WSR 17-17-040, Filed 8/9/2017, effective 9/9/2017Statutory Authority: RCW 90.48.035. 07-14-096 (Order 05-16), § 173-95A-560, filed 6/29/07, effective 7/30/07.