9 Va. Admin. Code § 5-80-1705

Current through Register Vol. 41, No. 6, November 4, 2024
Section 9VAC5-80-1705 - Control technology review
A. A major stationary source or major modification shall meet each applicable emissions limitation under the implementation plan and each applicable emissions standard and standard of performance under 40 CFR Parts 60, 61 and 63.
B. A new major stationary source shall apply best available control technology for each regulated NSR pollutant that it would have the potential to emit in significant amounts.
C. A major modification shall apply best available control technology for each regulated NSR pollutant for which it would result in a significant net emissions increase at the source. This requirement applies to each proposed emissions unit at which a net emissions increase in the pollutant would occur as a result of a physical change or change in the method of operation in the unit.
D. For phased construction projects, the determination of best available control technology shall be reviewed and modified as appropriate at the latest reasonable time that occurs no later than 18 months prior to commencement of construction of each independent phase of the project. At such time, the owner of the applicable stationary source may be required to demonstrate the adequacy of any previous determination of best available control technology for the source.

9 Va. Admin. Code § 5-80-1705

Derived from Virginia Register Volume 22, Issue 23, eff. September 1, 2006.

Statutory Authority

§ 10.1-1308 of the Code of Virginia; Clean Air Act (§§ 110, 112, 165, 173, 182 and Title V); 40 CFR Parts 51, 61, 63, 70 and 72.