Section 9VAC5-80-1200 - Compliance determination and verification by performance testing
A. For stationary sources other than those specified in subsection B of this section, compliance with standards of performance shall be determined in accordance with the provisions of 9VAC5-50-20 and shall be verified by performance tests in accordance with the provisions of 9VAC5-50-30.
B. For stationary sources of toxic pollutants, compliance with emission standards shall be determined in accordance with the provisions of 9VAC5-60-20 and shall be verified by emission tests in accordance with the provisions of 9VAC5-60-30.
C. Testing required by subsections A and B of this section shall be conducted by the owner within 60 days after achieving the maximum production rate at which the source will be operated, but not later than 180 days after initial startup of the source; and 60 days thereafter the department shall be provided by the owner with one or, upon request, more copies of a written report of the results of the tests.
D. For sources subject to the provisions of 40 CFR Part 60, 61 or 63, the compliance determination and performance test requirements of subsections A, B and C of this section shall be met as specified in those parts of Title 40 of the Code of Federal Regulations.
E. For sources other than those specified in subsection D of this section, the requirements of subsections A, B and C of this section shall be met unless the department:
1. Specifies or approves, in specific cases, the use of a reference method with minor changes in methodology;
2. Approves the use of an equivalent method;
3. Approves the use of an alternative method, the results of which the department has determined to be adequate for indicating whether a specific source is in compliance;
4. Waives the requirement for testing because, based upon a technical evaluation of the past performance of similar source types, using similar control methods, the department reasonably expects the source to perform in compliance with applicable standards; or
5. Waives the requirement for testing because the owner of the source has demonstrated by other means to the department's satisfaction that the source is in compliance with the applicable standard.
F. The provisions for the granting of waivers under subsection E of this section are intended for use in determining the initial compliance status of a source. The granting of a waiver does not obligate the department to grant any waivers once the source has been in operation for more than one year beyond the initial startup date.
G. The granting of a waiver under this section does not shield the source from potential enforcement of any permit term or condition, applicable requirement of the implementation plan, or any other applicable federal requirement promulgated under the federal Clean Air Act.

9 Va. Admin. Code § 5-80-1200

Derived from Virginia Register Volume 18, Issue 20, eff. September 1, 2002; amended, Virginia Register Volume 29, Issue 3, eff. November 7, 2012; Amended, Virginia Register Volume 39, Issue 5, eff. 11/23/2022.