Section 9VAC25-875-780 - [Effective 7/1/2024] Stormwater management permit applications
A. Approval of a permit application (registration statement) for a land-disturbing activity by a state agency or federal entity shall be subject to the following conditions:
1. The state agency or federal entity shall comply with all applicable requirements of the permit (9VAC25-880) and shall certify that all land clearing, construction, land development, and drainage will be done according to the permit.
2. The land development shall be conducted only within the area specified in the approved plan and covered by the permit.
3. No changes may be made to a plan for which a permit has been issued without review and written approval by the department.
4. The department shall be notified at least one week prior to the preconstruction meeting and at least one week prior to the commencement of land-disturbing activity.
5. The department shall conduct random inspections of the project to ensure compliance with the permit.
6. The department shall require inspections and reports from the state agency or federal entity responsible for compliance with the permit and to determine if the measures required in the permit provide effective stormwater management.
B. Compliance with the permit shall be subject to the following conditions:
1. Where inspection by the responsible state agency or federal entity reveals deficiencies in carrying out a permitted activity, the responsible state agency or federal entity shall ensure compliance with the issued permit, permit conditions, and plan specifications.
2. Where inspections by department personnel reveal deficiencies in carrying out the permit, the responsible state agency or federal entity shall be issued a notice to comply, with corrective actions specified and the deadline within which the work shall be performed.
3. Whenever the Commonwealth or any of its state agencies fail to comply within the time provided in a notice to comply, the director may petition the secretary of a given secretariat or an agency head for a given state agency for compliance. Where the petition does not achieve timely compliance, the director shall bring the matter to the Governor for resolution.
4. Where compliance for a state agency will require the appropriation of funds, the director shall cooperate with the appropriate agency head in seeking such an appropriation; where the director determines that an emergency exists, the director shall petition the Governor for funds from the Civil Contingency Fund or other appropriate source.
5. The department may also seek compliance through other means specified in the State Water Control Law.