9 Va. Admin. Code § 25-870-97

Current through Register Vol. 40, No. 22, June 17, 2024
Section 9VAC25-870-97 - [Repealed effective 7/1/2024] Stream channel erosion
A. Properties and receiving waterways downstream of any land-disturbing activity shall be protected from erosion and damage due to changes in runoff rate of flow and hydrologic characteristics, including, but not limited to, changes in volume, velocity, frequency, duration, and peak flow rate of stormwater runoff in accordance with the minimum design standards set out in this section.
B. The VSMP authority shall require compliance with subdivision 19 of 9VAC25-840-40 of the Erosion and Sediment Control Regulations, promulgated pursuant to the Erosion and Sediment Control Law.
C. The locality's VSMP authority may determine that some watersheds or receiving stream systems require enhanced criteria in order to address the increased frequency of bankfull flow conditions (top of bank) brought on by land-disturbing activities or where more stringent requirements are necessary to address total maximum daily load requirements or to protect exceptional waters. Therefore, in lieu of the reduction of the two-year postdeveloped peak rate of runoff as required in subsection B of this section, the land development project being considered shall provide 24-hour extended detention of the runoff generated by the one-year, 24-hour duration storm.
D. In addition to subsections B and C of this section, a locality's VSMP authority by local ordinance may in accordance with § 62.1-44.15:33 of the Code of Virginia, or the board by state regulation may, adopt more stringent channel analysis criteria or design standards to ensure that the natural level of channel erosion, to the maximum extent practicable, will not increase due to the land-disturbing activities. These criteria may include, but are not limited to, the following:
1. Criteria and procedures for channel analysis and classification.
2. Procedures for channel data collection.
3. Criteria and procedures for the determination of the magnitude and frequency of natural sediment transport loads.
4. Criteria for the selection of proposed natural or manmade channel linings.

9 Va. Admin. Code § 25-870-97

Derived From Virginia Register Volume 30, Issue 2, eff. October 23, 2013; Repealed, Virginia Register Volume 40, Issue 8, eff. 7/1/2024.

Statutory Authority: § 62.1-44.15:28 of the Code of Virginia; Chapters 68 and 758 of the 2016 Acts of Assembly.