9 Va. Admin. Code § 15-70-60

Current through Register Vol. 40, No. 22, June 17, 2024
Section 9VAC15-70-60 - Mitigation plan
A. If the department determines that significant adverse impacts to wildlife or historic resources or both are likely, then the applicant shall prepare a mitigation plan. The mitigation plan shall include a description of the affected wildlife or historic resources, or both, and the impact to be mitigated; a description of actions that will be taken to avoid the stated impact; and a plan for implementation. If the impact cannot reasonably be avoided, the plan shall include a description of actions that will be taken to minimize the stated impact and a plan for implementation. If neither avoidance nor minimization is reasonably practicable, the plan shall include a description of other measures that may be taken to offset the stated impact and a plan for implementation.
B. Mitigation measures for significant adverse impacts to wildlife shall include:
1. For state-listed T&E wildlife, the applicant shall take all reasonable measures to avoid significant adverse impacts or shall demonstrate in the mitigation plan what significant adverse impacts cannot practicably be avoided and why additional proposed actions are reasonable. These additional proposed actions may include best practices to avoid, minimize, or offset adverse impacts to resources analyzed pursuant to 9VAC15-70-40 A or C.
2. For proposed projects where the disturbance zone is located on or within one-half mile of a known or potential sea turtle nesting beach, the applicant shall take all reasonable measures to avoid significant adverse impacts or shall demonstrate in the mitigation plan what significant adverse impacts cannot practicably be avoided and why additional proposed mitigation actions are reasonable. Mitigation measures shall include the following:
a. Avoiding construction within likely sea turtle crawl or nesting habitats during the turtle nesting and hatching season (May 20 - October 31). If avoiding construction during this period is not possible, then conducting daily crawl surveys of the disturbance zone (May 20 - August 31) and one mile beyond the northern and southern reaches of the disturbance zone (hereinafter "sea turtle nest survey zone") between sunrise and 9 a.m. by qualified individuals who have the ability to distinguish accurately between nesting and non-nesting emergences.
b. If construction is scheduled during the nesting season, then including measures to protect nests and hatchlings found within the sea turtle nest survey zone.
c. Minimizing nighttime construction during the nesting season and designing project lighting during the construction and operational phases to minimize impacts on nesting sea turtles and hatchlings.
3. For projects located in part or in whole within zone 1, 2, 3, 4, 5, 10, 11, 12, or 14 on the Coastal Avian Protection Zones (CAPZ) map for which the tallest point of the built structures exceeds 200 feet, contribute $1,000.00 per megawatt of rated capacity, or partial megawatt thereof, to a fund designated by the department in support of scientific research investigating the impacts of projects in CAPZ on avian resources.
C. Mitigation measures for significant adverse impacts to historic resources shall include:
1. Significant adverse impacts to VLR-eligible or VLR-listed architectural resources shall be minimized, to the extent practicable, through design of the combustion energy project or the installation of vegetative or other screening.
2. If significant adverse impacts to VLR-eligible or VLR-listed architectural resources cannot be avoided or minimized such that impacts are no longer significantly adverse, then the applicant shall develop a reasonable and proportionate mitigation plan that offsets the significantly adverse impacts and has a demonstrable public benefit and benefit for the affected or similar resource.
3. If any identified VLR-eligible or VLR-listed archaeological site cannot be avoided or minimized to such a degree as to avoid a significant adverse impact, significant adverse impacts of the project will be mitigated through archaeological data recovery.

9 Va. Admin. Code § 15-70-60

Derived from Virginia Register Volume 29, Issue 24, eff. August 28, 2013.

Statutory Authority

§ 10.1-1197.6 of the Code of Virginia.