20 Va. Admin. Code § 5-315-40

Current through Register Vol. 40, No. 22, June 17, 2024
Section 20VAC5-315-40 - Conditions of interconnection
A. A prospective customer may begin operation of the generating facility on an interconnected basis when:
1. The customer has properly notified both the electric distribution company and energy service provider (in accordance with 20VAC5-315-30 ) of the customer's intent to interconnect.
2. If required by the electric distribution company's tariff, the customer has installed a lockable, electric distribution company accessible, load breaking manual disconnect switch at each of the facility's generators.
3. The licensed electrician who installs the customer's generator certifies, by signing the commission-approved notification form, that any required manual disconnect switch is being installed properly and that the generator has been installed in accordance with the manufacturer's specifications as well as all applicable provisions of the National Electrical Code. If the customer or licensed Virginia Class A or B general contractor installs the customer's generator, the signed final electrical inspection can be used in lieu of the licensed electrician's certification.
4. The vendor certifies by signing the commission-approved notification form that the generator being installed is in compliance with the requirements established by Underwriters Laboratories or other national testing laboratories in accordance with IEEE Standard 1547, Standard for Interconnecting Distributed Resources with Electric Power Systems, July 2003.
5. In the case of static inverter-connected generators with an alternating current capacity in excess of 10 kilowatts, the customer has had the inverter settings inspected by the electric distribution company. The electric distribution company may impose a fee on the customer of no more than $50 for each generator that requires this inspection.
6. In the case of nonstatic inverter-connected generators, the customer has interconnected according to the electric distribution company's interconnection guidelines and the electric distribution company has inspected all protective equipment settings. The electric distribution company may impose a fee on the customer of no more than $50 for each generator that requires this inspection.
7. The following requirements shall be met before interconnection may occur:
a. Electric distribution facilities and customer impact limitations. A customer's generator shall not be permitted to interconnect to distribution facilities if the interconnection would reasonably lead to damage to any of the electric distribution company's facilities or would reasonably lead to voltage regulation or power quality problems at other customer revenue meters due to the incremental effect of the generator on the performance of the electric distribution system, unless the customer reimburses the electric distribution company for its cost to accommodate the interconnection, including the reasonable cost of equipment required for the interconnection.
b. Secondary service, and service entrance limitations. The capacity of the generators at any one service location shall be less than the capacity of the electric distribution company-owned secondary service, and service entrance cable connected to the point of interconnection, unless the customer reimburses the electric distribution company for the reasonable cost of equipment required for the interconnection.
c. Transformer loading limitations. A customer's generator shall not have the ability to overload the electric distribution company's transformer, or any transformer winding, beyond manufacturer or nameplate ratings, unless the customer reimburses the electric distribution company for the reasonable cost of equipment required for the interconnection.
d. Integration with electric distribution company facilities grounding. The grounding scheme of each generator shall comply with IEEE 1547, Standard for Interconnecting Distributed Resources with Electric Power Systems, July 2003, and shall be consistent with the grounding scheme used by the electric distribution company. If requested by a prospective customer, the electric distribution company shall assist the prospective customer in selecting a grounding scheme that coordinates with its distribution system.
e. Balance limitation. The generator shall not create a voltage imbalance of more than 3.0% at any other customer's revenue meter if the electric distribution company transformer, with the secondary connected to the point of interconnection, is a three-phase transformer, unless the customer reimburses the electric distribution company for the reasonable cost of equipment required for the interconnection.
B. For an investor-owned electric distribution company, a prospective customer or small agricultural generator shall not be allowed to interconnect a generator to the distribution system if doing so will cause the total rated generating alternating current capacity of all interconnected net metered generators, as defined in 20VAC5-315-20, within that customer's electric distribution company's Virginia service territory to exceed 6.0%, in the aggregate, 5.0% that is available to all customers and 1.0% that is available only to low-income utility customers of that company's adjusted Virginia peak-load forecast for the previous year. In any case where a prospective customer has submitted a notification form required by 20VAC5-315-30 and that customer's interconnection would cause the total rated generating alternating current capacity of all interconnected net metered generators, as defined in 20VAC5-315-20, within that investor-owned electric distribution company's service territory to exceed the limitations described in this subsection, the electric distribution company shall, at the time it becomes aware of the fact, send written notification to the prospective customer and to the commission's Division of Public Utility Regulation that the interconnection is not allowed. In addition, upon request from any customer, the electric distribution company shall provide to the customer the amount of capacity still available for interconnection pursuant to § 56-594D of the Code of Virginia.
C. For an electric cooperative, a prospective customer shall not be allowed to interconnect a generator to the distribution system if doing so will cause the total rated generating alternating current capacity of all interconnected net metered generators, as defined in 20VAC5-315-20, within the cooperative's Virginia service territory to exceed the following percentages of system peak:
(i) for nonjurisdictional and nonprofit customers, 2.0% of the cooperative's system peak;
(ii) for residential customers, 2.0% of the cooperative's system peak; or
(iii) for other nonresidential customers, 1.0% of the cooperative's system peak. Such caps shall not decrease but may increase if the system peak in any year exceeds the previous year's system peak. For purposes of calculating the caps established in this subsection, all net energy metering shall be counted, whenever interconnected, and shall include net energy metering interconnected pursuant to § 56-594 of the Code of Virginia, agricultural net energy metering, and any net energy metering entered into with a third-party PPA provider registered pursuant to § 56-594.01K of the Code of Virginia. Net energy metering with nonjurisdictional customers entered into prior to July 1, 2019, may be counted toward the caps, in the discretion of the cooperative, as net energy metering if the nonjurisdictional customer takes service pursuant to a cooperative's net energy metering rider. Net energy metering with nonjurisdictional customers entered into on or after July 1, 2019, shall be counted toward the caps by default unless the cooperative has reason to exclude such net energy metering as subject to a separate contract or arrangement. Each electric cooperative governed by this section shall publish information regarding the calculation and status of its caps, or the electric cooperative's systemwide cap established via § 56-585.4 or 56-594.01G of the Code of Virginia if applicable, on the electric cooperative's website. In any case where a prospective customer has submitted a notification form required by 20VAC5-315-30 and that customer's interconnection would cause the total rated generating alternating current nameplate capacity of all interconnected net metered generators to exceed the percentages stated in this subsection, the electric cooperative shall, at the time it becomes aware of the fact, send written notification to the prospective customer and to the commission's Division of Public Utility Regulation that the interconnection is not allowed and shall update its website. In addition, upon request from any customer, the electric distribution company shall provide to the customer the amount of capacity still available for interconnection pursuant to § 56-594.01F of the Code of Virginia.
D. Neither the electric distribution company nor the energy service provider shall impose any charges upon a customer for any interconnection requirements specified by this chapter, except as provided under subdivisions A 5, A 6, and A 7 of this section, 20VAC5-315-50, and 20VAC5-315-70 as related to additional metering.
E. A customer shall immediately notify the electric distribution company of any changes in the ownership of, operational responsibility for, or contact information for any of the customer's generators.
F. The capacity of any generating facility installed between July 1, 2015, and July 1, 2020, shall not exceed the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available. In the certificated service territory of a Phase I Utility, the capacity of any generating facility installed pursuant to this section after July 1, 2020, shall not exceed 100% of the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available. In the certificated service territory of a Phase II Utility, the capacity of any generating facility installed pursuant to this section after July 1, 2020, shall not exceed 150% of the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available.

20 Va. Admin. Code § 5-315-40

Derived from Virginia Register Volume 16, Issue 20, eff. May 25, 2000; amended, Virginia Register Volume 21, Issue 18, eff. April 26, 2005; Volume 23, Issue 3, eff. September 26, 2006; Volume 24, Issue 26, eff. August 25, 2008; Volume 26, Issue 18, eff. April 28, 2010; Amended, Virginia Register Volume 30, Issue 23, eff. 7/1/2014; Amended, Virginia Register Volume 32, Issue 09, eff. 12/28/2015; Amended Virginia Register Volume 34, Issue 13, eff. 2/1/2018; Amended, Virginia Register Volume 36, Issue 14, eff. 3/1/2020; Amended, Virginia Register Volume 37, Issue 16, eff. 3/15/2021.

Statutory Authority: §§ 12.1-13 and 56-594 of the Code of Virginia.