TABLE 531.1 Microbial Toolbox Reporting Requirements | ||
TOOLBOX OPTION | OWNERS SHALL SUBMIT THE FOLLOWING INFORMATION: | ON THE FOLLOWING SCHEDULE: |
Alternative source or intake management | Verification that the waterworks has relocated the intake or adopted the intake withdrawal procedure reflected in monitoring results. | No later than the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Presedimentation | Monthly verification of the following: (i) Continuous basin operation; (ii) Treatment of 100% of the flow; (iii) Continuous addition of a coagulant; and (iv) At least 0.5-log mean reduction of influent turbidity or compliance with alternative performance criteria approved by the department. | Monthly reporting within 10 days following the month in which the monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Two-stage lime softening | Monthly verification of the following: (i) Chemical addition and hardness precipitation occurred in two separate and sequential softening stages before filtration; and (ii) Both stages treated 100% of the water treatment plant flow. | Monthly reporting within 10 days following the month in which the monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Bank filtration | Initial demonstration of the following: (i) Unconsolidated, predominantly sandy aquifer; and (ii) Setback distance of at least 25 ft. (0.5-log credit) or 50 ft. (1.0-log credit). | No later than the applicable treatment compliance date in 12VAC5-590-401 D 3. |
If monthly average of daily maximum turbidity is greater than 1.0 NTU then the waterworks shall report the result and submit an assessment of the cause. | Report within 30 days following the month in which the monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. | |
Combined filter performance | Monthly verification of CFE turbidity levels less than or equal to 0.15 NTU in at least 95% of the four-hour CFE measurements collected each month. | Monthly reporting within 10 days following the month in which the monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Individual filter performance | Monthly verification of the following: (i) Individual filter effluent turbidity levels less than or equal to 0.15 NTU in at least 95% of samples each month in each filter; and (ii) No individual filter greater than 0.3 NTU in two consecutive readings 15 minutes apart. | Monthly reporting within 10 days following the month in which the monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Demonstration of performance | Results from testing following a protocol approved by the department. | No later than the applicable treatment compliance date in 12VAC5-590-401 D 3. |
As required by the department, monthly verification of operation within conditions of the department's approval for demonstration of performance credit. | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. | |
Bag filters and cartridge filters | Demonstration that the following criteria are met: (i) Process meets the definition of bag or cartridge filtration; and (ii) Removal efficiency established through challenge testing that meets criteria in 12VAC5-590-401 E 6 a. | No later than the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Monthly verification that 100% of the water treatment plant flow was filtered. | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. | |
Membrane filtration | Results of verification testing demonstrating the following: (i) Removal efficiency established through challenge testing that meets criteria in subdivision B 5 of this section; and (ii) Integrity test method and parameters, including resolution, sensitivity, test frequency, control limits, and associated baseline. | No later than the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Monthly report summarizing the following: (i) All direct integrity tests above the control limit; and (ii) If applicable, any turbidity or alternative indirect integrity monitoring approved by the department that results in triggering direct integrity testing and the corrective action that was taken. | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. | |
Second stage filtration | Monthly verification that 100% of flow was filtered through both stages and the first stage was preceded by a coagulation step. | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Slow sand filtration (as secondary filter) | Monthly verification that both a slow sand filter and a preceding separate stage of filtration treated 100% of flow from surface water or GUDI. | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Chlorine dioxide | Summary of CT values for each day as described in 12VAC5-590-401 E 7 b (1). | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Ozone | Summary of CT values for each day as described in 12VAC5-590-401 E 7 b (2). | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
UV | Validation test results demonstrating operating conditions that achieve required UV dose. | No later than the applicable treatment compliance date in 12VAC5-590-401 D 3. |
Monthly report summarizing the percentage of water entering the distribution system that was not treated by UV reactors operating within validated conditions for the required dose as specified in 12VAC5-590-401 E 7 c (1). | Within 10 days following the month in which monitoring was conducted, beginning on the applicable treatment compliance date in 12VAC5-590-401 D 3. |
a = the value in subdivision C 3 a of this section.
b = the value in subdivision C 3 b of this section.
c = the value in subdivision C 3 c of this section.
d = the value in subdivision C 3 d of this section.
e = the value in subdivision C 3 e of this section.
12 Va. Admin. Code § 5-590-531