Utah Admin. Code 746-316-3

Current through Bulletin 2024-12, June 15, 2024
Section R746-316-3 - Submission of an Electrical Power Delivery Quality Plan
(1) A qualified utility shall submit an Electrical Power Delivery Quality Plan to the Commission on or before April 1, 2024 and biennially thereafter with subsequent Electrical Power Delivery Quality Plans due on or before April 1 of each even-numbered year.
(2) A qualified utility's Electrical Power Delivery Quality Plan must include:
(a) a description of the metrics a qualified utility uses to assess Power Quality against applicable Industry Standards;
(b) a description of the equipment the qualified utility uses to assess Power Quality and to otherwise comply with this rule;
(c) a description of the procedures and standards the qualified utility will use to assess an interconnection request to decrease the risk that the interconnected utility-scale generation facility will adversely affect electrical power delivery quality to customers;
(d) a description of the procedures and standards the qualified utility will use to address adverse effects to electrical power service quality that are caused by interconnected customer-owned generation systems, including instances where the adverse effects are discovered after the time of interconnection; and
(e) a description of proposed modifications or upgrades to facilities and preventive programs the qualified utility will implement to address any electrical power delivery quality issues that do not meet the qualified utility's interconnection policy or relevant Industry Standards.

Utah Admin. Code R746-316-3

Adopted by Utah State Bulletin Number 2023-21, effective 10/26/2023