Current through Bulletin No. 2024-21, November 1, 2024
Section R647-3-101 - Filing Requirements and Review Procedures1. Prior to commencement of operations, a Notice of Intention to Commence Small Mining Operations (FORM MR-SMO) containing all the required information must be filed with and determined complete by the Division and the Division shall have approved the form and amount of reclamation surety. It is recommended that the notice of intention be filed with the Division at least thirty (30) days prior to the planned commencement of operations.2. Within 15 days after receipt of a Notice of Intention, the Division will review the proposal and notify the operator in writing; 2.11. That the notice of intention is complete and all required information has been submitted; or,2.12. That the notice of intention is incomplete, and additional information as identified by the Division will be required. 2.12.111. The Division will review and respond to any subsequent filings of information within 10 working days of receipt.3. The Division will review and approve or disapprove: 3.11. The form and amount of reclamation surety (R647-3-111 ), and3.12. All variances requested from Rules R647-3-107, 108, and 109, regardless of the number of surface acres of disturbance planned.4. The operator must notify the Division no later than 30 days after beginning small mining operations.5. A permittee's authorization under a notice of intention to conduct small mining operations shall require the paying of permit fees as authorized by the Utah Legislature. The procedures for paying the permit fees are as follows: 5.11. The Division shall notify the operators of record annually of the amount of permit fees authorized by the Utah Legislature for small mining operations.5.12. Fees are due annually by the deadline in R647-3-117 for reports.6. A permittee may avoid payment of the fee by complying with the following requirements: 6.11. A permittee will notify the Division of a desire to close out a notice of intention by checking the appropriate box of the permit fees billing form.6.12. The permittee will then arrange with the Division for an onsite inspection of the site to assure that all required reclamation has been performed. If an inspection reveals that an area is not yet suitably reclaimed, then a new billing notice will be issued and the permittee will be given 30 days from the date of the onsite inspection to pay the fee.Utah Admin. Code R647-3-101
Amended by Utah State Bulletin Number 2020-04, effective 2/10/2020