Section R315-265-120 - Closure and Post-Closure - Certification of Completion of Post-Closure Care

No later than 60 days after the completion of the established post-closure care period for each hazardous waste disposal unit, the owner or operator shall submit to the Director, by registered mail, a certification that the post-closure care period for the hazardous waste disposal unit was performed in accordance with the specifications in the approved post-closure plan. The certification shall be signed by the owner or operator and a qualified Professional Engineer. Documentation supporting the Professional Engineer's certification shall be furnished to the Director upon request until he releases the owner or operator from the financial assurance requirements for post-closure care under Subsection R315-265-145(h).