Section R315-264-112 - Closure plan; Amendment of Plan
(a) Written plan.
(1) The owner or operator of a hazardous waste management facility shall have a written closure plan. In addition, certain surface impoundments and waste piles from which the owner or operator intends to remove or decontaminate the hazardous waste at partial or final closure are required by Subsections R315-264-228(c)(1)(i) and 258(c)(1)(i) to have contingent closure plans. The plan shall be submitted with the permit application, in accordance with Subsection R315-270-14(b)(13), and approved by the Director as part of the permit issuance procedures under Rule R315-124. In accordance with Section R315-270-32, the approved closure plan shall become a condition of any permit.
(2) Plans shall be consistent with Sections R315-264-111 through 115 and the applicable requirements of Sections R315-264-90 through 101, Sections R315-264-178, 197, 228, 258, 280, 310, 351, 601, and 1102. Until final closure is completed and certified in accordance with Section R315-264-115, a copy of the approved plan and all approved revisions shall be furnished to the Director upon request, including requests by mail.
(b) Content of plan. The plan shall identify steps necessary to perform partial and/or final closure of the facility at any point during its active life. The closure plan shall include, at least:
(1) A description of how each hazardous waste management unit at the facility will be closed in accordance with Section R315-264-111;
(2) A description of how final closure of the facility will be conducted in accordance with Section R315-264-111. The description shall identify the maximum extent of the operations which will be unclosed during the active life of the facility; and
(3) An estimate of the maximum inventory of hazardous wastes ever on-site over the active life of the facility and a detailed description of the methods to be used during partial closures and final closure, including, but not limited to, methods for removing, transporting, treating, storing, or disposing of all hazardous wastes, and identification of the type(s) of the off-site hazardous waste management units to be used, if applicable; and
(4) A detailed description of the steps needed to remove or decontaminate all hazardous waste residues and contaminated containment system components, equipment, structures, and soils during partial and final closure, including, but not limited to, procedures for cleaning equipment and removing contaminated soils, methods for sampling and testing surrounding soils, and criteria for determining the extent of decontamination required to satisfy the closure performance standard; and
(5) A detailed description of other activities necessary during the closure period to ensure that all partial closures and final closure satisfy the closure performance standards, including, but not limited to, ground-water monitoring, leachate collection, and run-on and run-off control; and
(6) A schedule for closure of each hazardous waste management unit and for final closure of the facility. The schedule shall include, at a minimum, the total time required to close each hazardous waste management unit and the time required for intervening closure activities which will allow tracking of the progress of partial and final closure. For example, in the case of a landfill unit, estimates of the time required to treat or dispose of all hazardous waste inventory and of the time required to place a final cover shall be included.
(7) For facilities that use trust funds to establish financial assurance under Section R315-264-143 or Section R315-264-145 and that are expected to close prior to the expiration of the permit, an estimate of the expected year of final closure.
(8) For facilities where the Director has applied alternative requirements at a regulated unit under Subsections R315-264-90(f), 264-110(c), and/or Subsection R315-264-140(d), either the alternative requirements applying to the regulated unit, or a reference to the enforceable document containing those alternative requirements.
(c) Amendment of plan. The owner or operator shall submit a written notification of or request for a permit modification to authorize a change in operating plans, facility design, or the approved closure plan in accordance with the applicable procedures in Rules R315-124 and 270. The written notification or request shall include a copy of the amended closure plan for review or approval by the Director.
(1) The owner or operator may submit a written notification or request to the Director for a permit modification to amend the closure plan at any time prior to the notification of partial or final closure of the facility.
(2) The owner or operator shall submit a written notification of or request for a permit modification to authorize a change in the approved closure plan whenever:
(i) Changes in operating plans or facility design affect the closure plan, or
(ii) There is a change in the expected year of closure, if applicable, or
(iii) In conducting partial or final closure activities, unexpected events require a modification of the approved closure plan.
(iv) The owner or operator requests the Director to apply alternative requirements to a regulated unit under Subsections R315-264-90(f), 264-110(c), and/or Subsection R315-264-140(d).
(3) The owner or operator shall submit a written request for a permit modification including a copy of the amended closure plan for approval at least 60 days prior to the proposed change in facility design or operation, or no later than 60 days after an unexpected event has occurred which has affected the closure plan. If an unexpected event occurs during the partial or final closure period, the owner or operator shall request a permit modification no later than 30 days after the unexpected event. An owner or operator of a surface impoundment or waste pile that intends to remove all hazardous waste at closure and is not otherwise required to prepare a contingent closure plan under Subsection R315-264-228(c)(1)(i) or Subsection R315-264-258(c)(1)(i), shall submit an amended closure plan to the Director no later than 60 days from the date that the owner or operator or Director determines that the hazardous waste management unit shall be closed as a landfill, subject to the requirements of Section R315-264-310, or no later than 30 days from that date if the determination is made during partial or final closure. The Director shall approve, disapprove, or modify this amended plan in accordance with the procedures in Rules R315-124 and 270. In accordance with Section R315-270-32, the approved closure plan shall become a condition of any permit issued.
(4) The Director may request modifications to the plan under the conditions described in Subsection R315-264-112(c)(2). The owner or operator shall submit the modified plan within 60 days of the Director's request, or within 30 days if the change in facility conditions occurs during partial or final closure. Any modifications requested by the Director shall be approved in accordance with the procedures in Rules R315-124 and 270.
(d) Notification of partial closure and final closure.
(1) The owner or operator shall notify the Director in writing at least 60 days prior to the date on which he expects to begin closure of a surface impoundment, waste pile, land treatment or landfill unit, or final closure of a facility with such a unit. The owner or operator shall notify the Director in writing at least 45 days prior to the date on which he expects to begin final closure of a facility with only treatment or storage tanks, container storage, or incinerator units to be closed. The owner or operator shall notify the Director in writing at least 45 days prior to the date on which he expects to begin partial or final closure of a boiler or industrial furnace, whichever is earlier.
(2) The date when he "expects to begin closure" shall be either:
(i) No later than 30 days after the date on which any hazardous waste management unit receives the known final volume of hazardous wastes, or if there is a reasonable possibility that the hazardous waste management unit will receive additional hazardous wastes, no later than one year after the date on which the unit received the most recent volume of hazardous wastes. If the owner or operator of a hazardous waste management unit can demonstrate to the Director that the hazardous waste management unit or facility has the capacity to receive additional hazardous wastes and he has taken all steps to prevent threats to human health and the environment, including compliance with all applicable permit requirements, the Director may approve an extension to this one-year limit; or
(ii) For units meeting the requirements of Subsection R315-264-113(d), no later than 30 days after the date on which the hazardous waste management unit receives the known final volume of non-hazardous wastes, or if there is a reasonable possibility that the hazardous waste management unit will receive additional non-hazardous wastes, no later than one year after the date on which the unit received the most recent volume of non-hazardous wastes. If the owner or operator can demonstrate to the Director that the hazardous waste management unit has the capacity to receive additional non-hazardous wastes and he has taken, and will continue to take, all steps to prevent threats to human health and the environment, including compliance with all applicable permit requirements, the Director may approve an extension to this one-year limit.
(3) If the facility's permit is terminated, or if the facility is otherwise ordered, by judicial decree or final administrative order, to cease receiving hazardous wastes or to close, then the requirements of Subsection R315-264-112(d) do not apply. However, the owner or operator shall close the facility in accordance with the deadlines established in Section R315-264-113.
(e) Removal of wastes and decontamination or dismantling of equipment. Nothing in Section R315-264-112 shall preclude the owner or operator from removing hazardous wastes and decontaminating or dismantling equipment in accordance with the approved partial or final closure plan at any time before or after notification of partial or final closure.

Utah Admin. Code R315-264-112

Adopted by Utah State Bulletin Number 2016-9, effective 4/15/2016