Utah Admin. Code 309-700-16

Current through Bulletin 2024-12, June 15, 2024
Section R309-700-16 - Construction

The Division of Drinking Water staff may conduct inspections and will report to the applicant and applicant's engineer. Contract change orders must be properly negotiated with the contractor and approved in writing. All Change orders must be reviewed by staff to determine eligibility for reimbursement within the SRF program requirements and determine there are sufficient funds in the amount authorized by the Drinking Water Board to complete the project as authorized. The applicant shall notify the Executive Secretary when the project is near completion and request a final inspection. When the project is complete, but before facilities can be placed into service, the recipient must request an operating permit in accordance with current Division of Drinking Water rules.

Utah Admin. Code R309-700-16

Adopted by Utah State Bulletin Number 2023-11, effective 5/22/2023