Utah Admin. Code 307-165-3

Current through Bulletin 2024-17, September 1, 2024
Section R307-165-3 - Notification of DAQ
(1) Unless otherwise specified by federal rule, the owner or operator shall notify the director of the date, time and place of stack testing no less than 30 days, before conducting a stack test, and provide a copy of the source test protocol to the director.
(2) The source shall obtain approval of the protocol from the director prior to conducting the test. The source test protocol shall:
(a) identify the reason for the test;
(b) outline each proposed test methodology;
(c) identify each stack to be tested; and
(d) identify each procedure to be used.
(3) The owner or operator shall attend a pretest conference if determined necessary by the director.

Utah Admin. Code R307-165-3

Amended by Utah State Bulletin Number 2020-16, effective 8/10/2020