Utah Admin. Code 307-801-17

Current through Bulletin No. 2024-21, November 1, 2024
Section R307-801-17 - Asbestos Information Distribution Requirements
(1) Utah Abatement/Renovation pamphlet. Utah asbestos abatement and renovation companies shall provide owners and occupants of single and multi-family residential structures with the Utah Abatement/Renovation Pamphlet "Asbestos Hazards During Abatement and Renovation Activities" when those structures will be re-occupied after the regulated activities are completed.
(2) No more than 60 days before beginning an abatement or renovation project in a regulated facility, the company performing the abatement or renovation project shall:
(a) Provide the owner of the regulated facility with the pamphlet, and comply with one of the following:
(i) Obtain, from the owner, a written acknowledgment that the owner has received the pamphlet; or
(ii) Obtain a certificate of mailing at least seven working days prior to the abatement or renovation project; and
(b) If the owner does not occupy the regulated facility, provide an adult occupant of the regulated facility with the pamphlet, and comply with one of the following:
(i) Obtain, from the adult occupant, a written acknowledgment that the occupant has received the pamphlet, or certify in writing that a pamphlet has been delivered to the regulated facility and that the company performing the abatement or renovation project has been unsuccessful in obtaining a written acknowledgment from an adult occupant. Such certification shall include the address of the unit undergoing abatement or renovation activities, the date and method of delivery of the pamphlet, names of the persons delivering the pamphlet, reason for lack of acknowledgment (e.g., occupant refuses to sign, no adult occupant available), the signature of a representative of the company performing the abatement or renovation project, and the date of signature; or
(ii) Obtain a certificate of mailing at least seven working days prior to the abatement or renovation project.
(3) Abatement or renovation projects in common areas. No more than 60 working days before beginning abatement or renovation projects in common areas of a regulated facility, the company performing the abatement or renovation project shall:
(a) Provide the owner with the pamphlet and comply with one of the following:
(i) Obtain, from the owner, a written acknowledgment that the owner has received the pamphlet; or
(ii) Obtain a certificate of mailing at least seven working days prior to the abatement or renovation project;
(b) Comply with one of the following:
(i) Notify in writing, or ensure written notification of, each regulated facility and make the pamphlet available upon request prior to the start of abatement or renovation project. Such notification shall be accomplished by distributing written notice to each affected unit in the regulated facility. The notice shall describe the general nature and locations of the planned abatement or renovation project, the expected starting and ending dates, how the occupant can obtain the pamphlet and a copy of the required records at no cost to the occupants; or
(ii) Post informational signs describing the general nature and locations of the abatement or renovation project and the anticipated completion date while the abatement or renovation project is ongoing. These signs shall be posted in areas where they are likely to be seen by the occupants of all of the affected units in the regulated facility. The signs shall be accompanied by a posted copy of the pamphlet or information about how interested occupants can review a copy of the pamphlet or obtain a copy from the abatement or renovation company at no cost to occupants. The signs shall also include information about how interested occupants can review a copy of the required records from the abatement or renovation company at no cost to the occupants;
(c) Prepare, sign, and date a statement describing the steps performed to notify all occupants of the regulated facility of the intended abatement or renovation project and to provide the pamphlet; and
(d) If the scope, locations, or expected starting and ending dates of the planned abatement or renovation project change after the initial notification, and the company provided written initial notification to each affected unit, the company performing the abatement or renovation project shall provide further written notification to the owners and occupants of the regulated facility of the revised information for the ongoing or planned activities. This subsequent notification shall be provided before the company performing the abatement or renovation project initiates work beyond that which was described in the original notice.
(4) Written acknowledgment. The written acknowledgments required by paragraphs R307-801-17(2)(a)(i), (2)(b)(i), and (3)(a)(i) shall:
(a) Include a statement recording the owner or occupant's name and acknowledging receipt of the pamphlet prior to the start of abatement or renovation project, or no later than the day after the start of an emergency abatement or renovation project, the address of the regulated facility undergoing an abatement or renovation project, the signature of the owner or occupant as applicable, and the date of signature;
(b) Be either a separate sheet or part of any written contract or service agreement for the abatement or renovation project; and
(c) Be written in the same language as the text of the contract or agreement for the abatement or renovation project or, in the case of a non-owner occupied regulated facility, in the same language as the lease or rental agreement or the pamphlet.

Utah Admin. Code R307-801-17

Amended by Utah State Bulletin Number 2016-11, effective 5/5/2016