Upon the request of an applicant, the permitting assistance coordinator shall provide the following:
This list informs the applicant of which permitting agencies or subdivisions must review and approve the proposed activity.
This statement gives the applicant an initial indication of how the proposed activity should be designed, carried out, or maintained to receive the permits or approvals
This schedule informs the applicant of the general timeline and sequence in which the permitting agencies or subdivisions will likely review the proposed activity and grant or deny the applications for permits or other approvals
This list informs the applicant of the project-specific information and data that must be collected and included in each application before the permitting agencies or subdivisions can begin the review and approval process.
This gives the applicant the opportunity to obtain explanations or clarifications about the information or data specifically required for each and how to complete and submit each application.
31 Tex. Admin. Code § 28.13