30 Tex. Admin. Code § 330.123

Current through Reg. 49, No. 24; June 14, 2024
Section 330.123 - Pre-Operation Notice

The owner or operator shall provide written notice in the form of a soil liner evaluation report as described in § 330.341 of this title (relating to Soil Liner Evaluation Report and Geomembrane Liner Evaluation Report) of the final construction and lining of a new disposal area (sector) to the executive director for review 14 days prior to the placement of waste. The executive director has 14 days to provide a verbal or written response. If by the end of the 14th day following the executive director's receipt of the report no comments are received, the operator may begin placing waste. This provision is not applicable to the initial opening of a municipal solid waste landfill.

30 Tex. Admin. Code § 330.123

The provisions of this §330.123 adopted to be effective March 27, 2006, 31 TexReg 2502