30 Tex. Admin. Code § 113.2305

Current through Reg. 49, No. 44; November 1, 2024
Section 113.2305 - When must I submit my waste management plan?

You must submit a waste management plan no later than 60 days following the initial performance test as specified in Table 5 in § 113.2357 of this title (relating to Tables Relating to Division 5). Section 113.2321 of this title (relating to By what date must I conduct the initial performance test?) specifies the date by which you are required to conduct your performance test.

30 Tex. Admin. Code § 113.2305

The provisions of this §113.2305 adopted to be effective May 14, 2009, 34 TexReg 2771