30 Tex. Admin. Code § 113.2120

Current through Reg. 49, No. 24; June 14, 2024
Section 113.2120 - After the required date for operator certification, who may operate the municipal waste combustion unit?

After the required date for full or provisional certification, you must not operate your municipal waste combustion unit unless one of four employees is on duty:

(1) A fully certified chief facility operator.
(2) A provisionally certified chief facility operator who is scheduled to take the full certification exam.
(3) A fully certified shift supervisor.
(4) A provisionally certified shift supervisor who is scheduled to take the full certification exam.

30 Tex. Admin. Code § 113.2120

The provisions of this §113.2120 adopted to be effective May 14, 2009, 34 TexReg 2771