30 Tex. Admin. Code § 113.2107

Current through Reg. 49, No. 24; June 14, 2024
Section 113.2107 - How do I comply with the increment of progress for awarding contracts?

You must submit to the executive director a signed copy of the contracts awarded to initiate onsite construction, initiate onsite installation of emission control equipment, and incorporate process changes. Submit the copy of the contracts with the notification that the increment of progress has been achieved to the executive director. You do not need to include documents incorporated by reference or the attachments to the contracts.

30 Tex. Admin. Code § 113.2107

The provisions of this §113.2107 adopted to be effective May 14, 2009, 34 TexReg 2771