30 Tex. Admin. Code § 113.2101

Current through Reg. 49, No. 23; June 7, 2024
Section 113.2101 - What are my requirements for meeting increments of progress and achieving final compliance?
(a) Class I units. If you plan to achieve compliance more than 1 year following the effective date of state plan approval and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operating permit if a permit modification is required, you must meet five increments of progress:
(1) Submit a final control plan.
(2) Submit a notification of retrofit contract award.
(3) Initiate onsite construction.
(4) Complete onsite construction.
(5) Achieve final compliance.
(b) Class II units. If you plan to achieve compliance more than 1 year following the effective date of state plan approval and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operating permit if a permit modification is required, you must meet two increments of progress:
(1) Submit a final control plan.
(2) Achieve final compliance.

30 Tex. Admin. Code § 113.2101

The provisions of this §113.2101 adopted to be effective May 14, 2009, 34 TexReg 2771