Tenn. Comp. R. & Regs. 1220-04-04-.33

Current through June 26, 2024
Section 1220-04-04-.33 - POST-INSTALLATION INSPECTIONS
(1) Post-installation inspections are to be made to determine proper operation and wiring connections and must be made within sixty (60) days after installation by a qualified person who, whenever possible, should be someone other than the original installer. The following equipment is subject to post-installation inspections:
(a) Meters with associated instrument transformers and phase shifting transformers.
(b) Kilovar-hour meters.
(c) Demand meters.
(d) Direct current watt-hour meters.

Tenn. Comp. R. & Regs. 1220-04-04-.33

Original rule certified May 9, 1974. Amendment filed October 30, 2000; effective January 13, 2001.

Authority: T.C.A. § 65-2-102.