Tenn. Comp. R. & Regs. 0400-53-01-.01

Current through October 22, 2024
Section 0400-53-01-.01 - TIME LIMIT FOR WELL COMPLETION

All wells drilled in connection with the production of oil and gas, unless plugged in accordance with well abandonment procedures as stated in Chapter 0400-52-09, shall be completed within 1 year from cessation of drilling unless the operator is following the procedures outlined in Rule 0400-52-09-.06 Temporary Abandonment.

Tenn. Comp. R. & Regs. 0400-53-01-.01

Original rule filed March 20, 2013; effective June 18, 2013.