S.D. Admin. R. 74:56:03:19

Current through Register Vol. 51, page 71, January 6, 2025
Section 74:56:03:19 - Requirements for release detection

Requirements for release detection shall consist of the following:

(1) AST systems must have equipment for release detection as required in § 74:56:03:04, including one or more of the following:
(a) Perforated gravity collection pipes or channels in a concrete foundation pad which can be monitored for the presence of a release;
(b) Internal systems designed to detect any changes in regulated substance level, such as in-tank monitors, capable of continuous monitoring and connected to an external alarm system;
(c) External systems designed to detect any releases; or
(d) Comparable release detection systems as approved by the department.

Department approval is required prior to the installation of the release detection systems.

S.D. Admin. R. 74:56:03:19

14 SDR 76, effective 11/29/1987; 18 SDR 62, effective 10/10/1991; transferred from

General Authority: SDCL 34A-2-93, 34A-2-101.

Law Implemented: SDCL 34A-2-100, 34A-2-101.

Note: It is recommended that owners or operators conduct hydrogeologic investigations to determine proper siting of release detection systems.