Section 74:56:03:09 - Site assessment required

Proposed sites for new AST systems shall be assessed to establish background conditions if contamination is suspected. The site assessment report must be made available to the department at least 30 days before installation of the AST system.

S.D. Admin. R. 74:56:03:09

14 SDR 76, effective 11/29/1987; 18 SDR 62, effective 10/10/1991; transferred from

General Authority: SDCL 34A-2-93, 34A-2-101.