S.D. Admin. R. 74:54:02:05

Current through Register Vol. 51, page 34, September 9, 2024
Section 74:54:02:05 - Separate groundwater discharge plan not required for certain activities

The following do not require a separately approved groundwater discharge plan if the discharge activity is subject to a review by the secretary as described in this chapter for conformance to chapter 74:54:01:

(1) Underground injection control (UIC) wells permitted under chapter 74:55:02 and Class V UIC wells permitted by the EPA;
(2) Individual and small on-site wastewater systems in compliance with chapter 74:53:01; and
(3) Wastewater treatment and disposal facilities with plans and specifications approved prior to construction by the secretary and which have been issued either a surface water discharge permit in accordance with chapter 74:52:01 or an EPA NPDES permit. Wastewater treatment and disposal facilities that are designed to discharge to groundwater must submit a groundwater discharge plan application.

S.D. Admin. R. 74:54:02:05

14 SDR 86, effective 12/24/1987; 18 SDR 128, effective 2/11/1992; transferred from

General Authority: SDCL 34A-2-28.

Law Implemented: SDCL 34A-2-24, 34A-2-27, 34A-2-36.1.

Construction of control facilities, ch 74:53:03.