The owner and operator of a new discharge facility that is not exempted by § 74:54:02:04 and facilities that discharges waste or pollutants that may move directly or indirectly into groundwater, including land application of wastes, waste storage pits, waste storage piles, landfills and dumps, feedlots, mining and milling operations, and concentrated animal feeding operations as described in SDCL 34A-3A-24, must apply to the secretary for an approved groundwater discharge plan at least 180 days before any discharge. The owner and operator of a discharge facility that is discharging waste or pollutants before the effective date of these rules or within 120 days after their effective date who is not exempt or excluded by § 74:54:02:04 must submit an application for a groundwater discharge plan within 60 days after receipt of written notice from the secretary that an approved groundwater discharge plan is required.
S.D. Admin. R. 74:54:02:02
General Authority: SDCL 34A-2-28.
Law Implemented: SDCL 34A-2-39, 34A-2-39.1, 34A-3A-24.