S.D. Admin. R. 74:36:20:05.01

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:36:20:05.01 - Procedures for an insignificant increase in allowable emissions

The department shall take the following final action on the proposed insignificant increase in allowable emissions within 90 days after receipt of a complete application for an insignificant increase in allowable emissions:

(1) Issue the construction permit as proposed;
(2) Deny the application for a construction permit; or
(3) Determine the application should be processed as a construction permit following the procedural requirements in §§ 74:36:20:06 to 74:26:20:10, inclusive.

The secretary shall issue the construction permit for an insignificant increase in allowable emissions without the procedural requirements applicable to obtaining a construction permit.

S.D. Admin. R. 74:36:20:05.01

42 SDR 52, effective 10/13/2015

General Authority: SDCL 34A-1-6, 34A-1-21.

Law Implemented: SDCL 34A-1-21.