S.D. Admin. R. 74:36:18:03

Current through Register Vol. 51, page 57, November 12, 2024
Section 74:36:18:03 - Permit required

Beginning on August 1, 2002, no state facility or state contractor may engage in any construction activity or continuous operation activity within the Rapid City air quality control zone which may cause fugitive emissions of particulate to be released into the ambient air without first obtaining a permit issued by the board or the secretary. The secretary may extend the August 1, 2002, deadline for 60 days if circumstances warrant an extension.

S.D. Admin. R. 74:36:18:03

28 SDR 178, effective 7/1/2002.

General Authority: SDCL 34A-1-6, 34A-1-21.

Law Implemented: SDCL 34A-1-21.

Note: The procedural requirements for obtaining a construction activity or continuous operation activity permit under this chapter will be the same as the procedural requirements for a minor source, such as a timely and complete application, completeness review, public participation, and department recommendation, as outlined in §§ 74:36:04:06 and 74:36:04:08 to 74:36:04:14, inclusive.