S.D. Admin. R. 74:36:07:127

Current through Register Vol. 50, page 162, June 24, 2024
Section 74:36:07:127 - Existing municipal solid waste landfill revised plan submittal

The owner or operator of an existing municipal solid waste landfill that meets the requirements of § 74:36:07:105 shall submit a revised design plan to the Secretary for approval:

1. At least 90 days before expanding operations to an area not covered by the previously approved design plan; and
2. Prior to installing or expanding the gas collection system in a way that is not consistent with the previously approved design plan.

S.D. Admin. R. 74:36:07:127

46 SDR 064, effective 11/25/2019

General Authority: SDCL 34A-1-6.