All terms and conditions of a Part 70 operating permit issued pursuant to this article, including any provisions designed to limit a source's potential to emit, are federally enforceable, except those conditions imposed by the department that are not required under the Clean Air Act. The conditions imposed by the department that are not required under the Clean Air Act must be specifically designated as not being federally enforceable.
S.D. Admin. R. 74:36:05:50
General Authority: SDCL 34A-1-6.
Law Implemented: SDCL 34A-1-6.