The department shall make its final permit decision within 30 days of the end of the public comment period on a draft permit. The department shall notify, in writing, the applicant and each person or affected state that submitted written comments or requested notice of the final permit decision. The notice shall include reference to the procedures for contesting the final permit decision and requesting a hearing in accordance with article 74:09. For the purpose of this section, the final permit decision means proposing a permit, denying a permit, or terminating a permit.
The proposed Part 70 operating permit must be submitted to EPA within 30 days of notifying the applicant and each person or affected state that submitted written comments or requested notification of the final permit decision except under the following conditions:
S.D. Admin. R. 74:36:05:20.01
General Authority: SDCL 34A-1-6, 34A-1-21.
Law Implemented: SDCL 1-26-27, 1-26-29, 34A-1-21.