If permitted injection volumes, pressures, and fluid characteristics remain unchanged, a permit to inject may be transferred to a new owner or operator by using the transfer of ownership or operation procedure in § 74:12:04:18.
If there will be a major modification in permitted injection volumes, pressures, or fluid characteristics, the new owner or operator must submit an application for a permit to inject modification pursuant to this chapter. The application must be approved by the secretary before initiating the proposed changes at the well.
S.D. Admin. R. 74:12:07:06
General Authority: SDCL 45-9-11, 45-9-13, 45-9-73.
Law Implemented: SDCL 45-9-11, 45-9-13, 45-9-73.