S.D. Admin. R. 74:05:11:12.03

Current through Register Vol. 51, page 54, October 28, 2024
Section 74:05:11:12.03 - Environmental determinations

For projects that pursuant to the Act require an environmental review, the environmental review process must be completed before the closing of the loan. For projects requiring a Categorical Exclusion, the process is considered complete upon publication of the Categorical Exclusion. For projects requiring a Finding of No Significant Impact determination, the process is considered complete when the 30-day comment period following the publication of the Finding of No Significant Impact has elapsed and any comments have been addressed.

S.D. Admin. R. 74:05:11:12.03

36 SDR 208, effective 6/28/2010.

General Authority: SDCL 46A-1-60.1 to 46A-1-60.3.

Law Implemented: SDCL 46A-1-60.1 to 46A-1-60.3.