S.D. Admin. R. 74:02:01:06

Current through Register Vol. 51, page 54, October 28, 2024
Section 74:02:01:06 - Application for water permit furnished by chief engineer - Method of completion - Fee required

An application for a water permit and instruction sheet shall be furnished by the chief engineer upon request. The completed application submitted to the chief engineer must be legible and include the name of the applicant or applicant's legal agent. Supplements may be attached if there is not sufficient space on the forms. The applicant may confer with the chief engineer on questions concerning preparation of the application. The fee required by SDCL 46-2-13 must be submitted with the application unless the applicant is a governmental entity. Fees from governmental entities may be submitted after an application, but must be submitted prior to issuance of the permit.

S.D. Admin. R. 74:02:01:06

SL 1975, ch 16, § 1; transferred from § 52:01:01:04, effective 7/1/1979; 9 SDR 96, effective 1/30/1983; 10 SDR 27, effective 9/26/1983; 13 SDR 49, effective 10/27/1986; 13 SDR 129, 13 SDR 141, effective 7/1/1987; 15 SDR 158, effective 4/23/1989; 39 SDR 37, effective 9/10/2012.

General Authority: SDCL 46-2-5.

Law Implemented: SDCL 46-2-13, 46-5-10, 46-5-11, 46-6-3.