S.D. Admin. R. 61:24:06:04

Current through Register Vol. 51, page 57, November 12, 2024
Section 61:24:06:04 - Verification, certification, or denial

Upon receipt of an application, the department administrator shall verify the facts set forth. The department shall certify the bond pool if, upon verification, all requirements of SDCL 32-6B-7.1 and this chapter are met. If the application does not meet the requirements of SDCL 32-6B-7.1 and this chapter, the department shall notify the applicant in writing of the deficiencies or reasons for not certifying. The applicant in accordance with SDCL chapter 1-26 may request a hearing within 30 days after receipt of the written notice of deficiencies.

S.D. Admin. R. 61:24:06:04

17 SDR 98, effective 1/15/1991.

General Authority: SDCL 32-6B-7.1.

Law Implemented: SDCL 32-6B-7.1.