S.D. Admin. R. 24:52:14:07

Current through Register Vol. 50, page 162, June 24, 2024
Section 24:52:14:07 - Violation of covenants - Board notification

Within 60 days after being notified in writing that a covenant has been violated, the office or board shall initiate a project review. The board shall issue a determination within 180 days as to whether there has been an adverse effect on the tax-certified property. The board shall notify the owner of record of the tax-certified property of its determination within 30 days after issuance. The owner must provide any information and document requested in writing by the office or board that is relevant to the investigation.

S.D. Admin. R. 24:52:14:07

21 SDR 50, effective 9/21/1994; 24 SDR 73, effective 12/4/1997.

General Authority: SDCL 1-19A-5, 1-19A-29.

Law Implemented: SDCL 1-19A-20 to 1-19A-24.